Case Study: Aviation Terminal
In the fast-paced world of aviation, precision and speed are paramount. We're thrilled to share our latest milestone – a groundbreaking Scan-to-BIM project that's set to redefine industry standards. In just 5 weeks, we transformed an expansive 110,000 sqft aviation terminal into a meticulously detailed, Level of Development 300+ BIM model. This case-study unveils how we're soaring to new heights in the aviation sector.
Project Overview:
Project Type: Aviation Terminal
Size: Over 110,000 sqft
Scan Duration: Completed in 3 days with a 2-man team
Complex MEPF Scanning: Including above and below ceiling tile, even in active public areas
BIM Creation:
Architectural & Structural Model: Completed in 3 weeks
MEPF Model: Finalized in 1 week
Quality Control: Finalized 1 week
Total Project Duration: Approximately 5 weeks
Model Specifications:
Level of Development (LoD): 300+
Compliant with Port Authority BIM Standard
Serves as Foundation for Terminal BIM
Model Contents:
Includes office, restaurant, retail, industrial, structural, MEPF, and transportation components
Accuracy Assurance:
Tolerance Standards: Maintained throughout the entire model
Point Cloud: 0”-⅛”
Revit Model: 0”-½”